In construction contracts, extensions of time are formalized by a document known as:

  1. Easement

  2. Supplementary condition

  3. Squinter

  4. Change order

The correct answer is: Change order

In construction contracts, a change order serves as the formal document used to modify the original contract terms, including extensions of time. This document is vital for adjusting the timeline due to unforeseen circumstances, design changes, or additional work required beyond the original scope. When a delay occurs, such as due to weather, material shortages, or owner-directed changes, the contractor submits a change order to request additional time. This ensures that both the contractor and the owner have a clear, mutual understanding of the revised schedule and any potential cost implications. While supplementary conditions may contain specific adjustments to the original contract requirements, they do not specifically address time extensions. An easement relates to property rights and does not cover contract modifications. The term "squinter" is not relevant in this context, as it does not pertain to construction terminology or contracts. Thus, the use of change orders is essential for clear communication and legal documentation regarding modifications to project timelines and scopes within the construction industry.