What can be inferred about the stick-by-stick method for estimating costs?

  1. It is time-consuming but accurate

  2. It is only suitable for small jobs

  3. It ignores market price fluctuations

  4. It is outdated and rarely used

The correct answer is: It is time-consuming but accurate

The stick-by-stick method for estimating costs is known for its thoroughness, as it involves evaluating each individual component or element of a construction project. This process meticulously accounts for all materials and labor required, leading to a high level of accuracy in the cost estimation. While it does take a considerable amount of time to analyze each item in detail, the precision it offers makes it a valuable method, particularly in complex projects where accurate budgeting is crucial. This method is often favored when the specifics of a project must be tightly controlled, reflecting why it is characterized as both time-consuming and accurate. The other options reflect aspects that do not align with the characteristics of the stick-by-stick method, such as its applicability to project size, its adaptability to market conditions, and its relevance in modern practices.