What document formalizes extensions of time in construction contracts?

  1. Easement

  2. Supplementary condition

  3. Squinter

  4. Change order

The correct answer is: Change order

A change order is the document that formalizes extensions of time in construction contracts. It is an essential tool used in the construction industry to manage modifications to the original contract, which can include changes in scope, design, or schedule. When delays occur due to unforeseen circumstances, the contractor can request additional time to complete the work without incurring penalties. Submitting a change order initiates a process that allows both the contractor and the owner to agree on the new timeline and any associated costs. This legal document ensures that both parties acknowledge and accept the revised terms, thus protecting their interests and allowing the project to move forward smoothly. In contrast, an easement relates to the right to cross or use someone else's land for a specific purpose and has no connection to time extensions in construction. Supplementary conditions may involve additional terms and stipulations that adjust the general contract terms but do not themselves formalize time extensions. A squinter is not a recognized term in construction contracts and may not refer to any relevant document.