What is typically indicated by a change order on a construction project?

  1. A scope change

  2. A cost increase

  3. Completion of work

  4. A delay in schedule

The correct answer is: A scope change

A change order on a construction project typically indicates a scope change. This document is crucial in the construction process as it formalizes amendments to the original contract terms. When a project encounters new requirements or adjustments in the work that differ from the initial plan, a change order is utilized to document those modifications. These adjustments can arise from various factors, such as client requests for additional features, unforeseen site conditions, or regulatory changes that necessitate alterations to the originally agreed-upon work. The change order not only serves to inform all parties involved about the scope modifications but also reflects how those changes will affect the overall project. While a change order may also lead to a cost increase or delays in the schedule, its primary function is to address the alterations in the work scope. Therefore, recognizing a change order as an indication of a scope change is critical for understanding project management and contracts in the construction industry.