When is the best time for a contractor to let their attorney see a construction contract?

  1. After the contract is signed by the client

  2. After the building permit is obtained

  3. After the contract is prepared but before signing

  4. Before clients see the contract

The correct answer is: After the contract is prepared but before signing

The best time for a contractor to let their attorney see a construction contract is after the contract is prepared but before signing it. This is crucial because it allows the attorney to review the terms and conditions of the contract to ensure they are fair and legally sound. Doing this prior to signing can help identify any potential issues, ambiguities, or unfavorable terms that could lead to disputes down the line. By consulting with an attorney at this stage, the contractor can make any necessary changes or negotiate terms with the client before the contract becomes legally binding. Reviewing the contract at this phase also helps the contractor understand their rights and obligations, ultimately leading to a stronger and more transparent agreement with the client. This proactive approach helps minimize legal risks and can prevent costly litigation or misunderstandings in the future.