Prepare for the Utah Contractor Exam with comprehensive quizzes and study resources. Gain confidence by accessing multiple-choice questions designed to enhance your knowledge and skills for the licensing exam.

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


Where would a contractor go to verify that building permits were issued for all construction work done on a house?

  1. Agency that granted initial permit

  2. State Department of Housing

  3. OSHA

  4. County Recorder's office

The correct answer is: Agency that granted initial permit

The agency that granted the initial permit is the most suitable place for a contractor to verify that building permits were issued for all construction work done on a house. This agency is responsible for the oversight and regulation of permitting processes within its jurisdiction. By consulting this agency, a contractor can obtain official records of permits, modifications, inspections, and any other related documentation necessary to ensure compliance with local building codes and regulations. Given its direct involvement in the permitting process, it holds the authoritative records and information relevant to construction projects, making it the best source for verification. While other options may hold some relevance in broader construction or housing contexts, they do not specifically focus on the verification of building permits like the initial permitting agency does. The State Department of Housing deals more with housing policies and regulations, OSHA's focus is on workplace safety, and the County Recorder's office typically handles property records but does not specifically focus on construction permits.